Infrastructure · Data Centers · Google · Microsoft · Neoclouds

Crusoe Says Google Bought Its Wyoming Site, a Day After Google Pledged $17 Billion There. Microsoft Passed on an Option to More Than Double Its Nscale Texas Lease, the FT Reports.

Kira Nolan··6 min read

On Thursday, November 5, Google announced its first data center in Wyoming: a $17 billion campus in Laramie County, near Cheyenne. On Friday, November 6, Crusoe said Google had acquired its data center site in southeast Wyoming. Neither company disclosed a price.

That sale ends a project Crusoe announced with Tallgrass in July 2025. In June, Bloomberg reported that Crusoe had been pushed aside there. The sale also landed in the same week that Microsoft, which Bloomberg says helped spark the boom in independent data center developers known as neoclouds, was reported to be pulling back from several of them.

Put the two together and the message to independent developers is blunt. Hyperscalers still want the capacity. They are less willing to rent it from someone else.

What Google Bought

Crusoe's own announcement frames the sale as a handoff. The deal, it says, completes Crusoe's pre-development work on the site: site selection, government approvals and a hybrid power strategy developed with Tallgrass Energy. CEO Chase Lochmiller said Crusoe's pre-construction work on origination, entitlement and de-risking set the project up for construction and eventual operation. He added that Crusoe has "more than 6 GW contracted and over 40 GW in our pipeline."

Google's post, by Steve Walter, its VP of global infrastructure and energy, does not mention Crusoe at all. It names four partners: Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital. Bloom Energy will make the fuel cells.

The power plan is the most specific part of Google's post. AEP is contracted for a 702 MW fuel cell development, running on natural gas, with carbon capture and storage at Tallgrass's nearby sequestration hub. Google calls it the largest planned development of its kind to date. It says the project brings its total contracted carbon capture capacity to nearly 1 gigawatt. More power comes from gas generators run by Tallgrass and Black Hills. The data center will be air-cooled, and Google says it "will pay for 100% of the power we use."

How Crusoe Lost the Customer

When Crusoe and Tallgrass announced the campus on Thursday, July 24, 2025, they described a 1.8 gigawatt AI campus in southeast Wyoming that could scale to 10 gigawatts.

On Thursday, June 11, 2026, Bloomberg reported that Crusoe had been pushed aside at the project after Google, which it had failed to sign as a customer, raised concerns about costs and the timetable under Crusoe's watch, citing people familiar with the situation. Crusoe said at the time that it had paused development at its customer's request. Friday's sale came 148 days after that report.

Crusoe has not lost Google as a client. It says it is still the developer of Google's campus under construction in Armstrong County, outside Amarillo, Texas. TechCrunch also notes Crusoe raised a $3.9 billion round in September, and its customers include Oracle and OpenAI at Abilene, Texas, plus Microsoft and Meta.

Microsoft's Week

On Thursday, November 5, the Financial Times reported that Microsoft declined to expand its Texas lease with Nscale at the Ward County site. The option would have more than doubled the existing contract. The original October 2025 deal covered about 240 MW, with an option on a second phase that was described as 700 MW at the time. Nscale told the FT the option was closer to 500 MW. The report, which comes ahead of what it called a roughly $35 billion Nscale IPO, says the decision will not affect Nscale's total backlog of $103 billion.

The same day, Bloomberg reported that Microsoft is tightening oversight of some projects from Nebius, IREN and Nscale and has walked away from some. Microsoft earlier canceled a roughly $3 billion Nscale deal for a UK data center over grid power delays, Bloomberg says. A Microsoft spokesperson told Bloomberg it manages partners "against our requirements and customer demand" and called these "normal and responsible practices." IREN and Nebius shares each fell about 20 percent on Thursday, Bloomberg reports.

MoveDateSizeSource
Crusoe and Tallgrass announce Wyoming campusJul 24, 20251.8 GW, scalable to 10 GWTallgrass release
Crusoe pushed aside after Google concernsJun 11, 2026Costs and timetable citedBloomberg, people familiar
Google announces Wyoming data centerNov 5, 2026$17 billion; 702 MW fuel cellsGoogle
Microsoft declines Nscale Texas optionReported Nov 5, 2026Would have more than doubled a ~240 MW leaseFinancial Times
Microsoft tightens neocloud oversightReported Nov 5, 2026Nebius, IREN, Nscale projectsBloomberg
Google acquires Crusoe's Wyoming siteNov 6, 2026Price not disclosedCrusoe

The Politics Around It

Google announced a $17 billion data center two days after an election that went badly for data centers. Reuters, citing Ballotpedia, says 41 data center related ballot measures were voted on that week and all but one went against data centers. Bloom Energy shares fell more than 14 percent on Thursday on fears of new restrictions, Reuters reports.

Wyoming is a different place to build. Donald Trump won more than 70 percent of its 2024 presidential vote, Reuters notes. Google's post reads like it was written for the week: it lists more than 200 residents met in Laramie County, an air-cooled design, a promise to pay for all the power it uses and the infrastructure its growth requires, and a community council with its partners.

Our Take

Crusoe's announcement calls this a completed engagement. Bloomberg's June reporting describes a developer that could not sign its customer and was pushed out. Both can be true, and the gap between them is the lesson for every neocloud. Finding land, winning approvals and designing a power plan is real work, and Google clearly wanted the result. By Bloomberg's account, it did not want Crusoe running the build.

That is the model I expect to spread. Independent developers do the slow, local, politically exposed part. Then the hyperscaler buys the site or keeps the developer on a short leash, as Microsoft is now doing with Nebius, IREN and Nscale. The developer gets paid for origination. It does not get the long lease that justified its valuation.

The timing makes it sharper. After Tuesday's votes, the risk in a data center sits in permits, power and local politics, and a hyperscaler with a $17 billion budget and its own power deals can carry that risk more cheaply than a neocloud borrowing against a single tenant. Microsoft's pullback says the same thing from the other side: when third-party capacity slips, the buyer takes back control.

For Nscale, this is the risk we flagged when it filed its S-1 in September: two customers made up about 85 percent of its backlog, and one of them could walk. Nothing reported this week says Microsoft walked from its existing Texas contract. It declined the next phase. That is a smaller event, and still the one investors were told to watch.

Three Signposts for the Next 60 Days

First, whether Crusoe or Google discloses the sale price, which would show what pre-development work on a gigawatt-scale site is worth. Second, whether Nscale names a new customer for the Ward County capacity before it prices its listing. Third, whether another hyperscaler buys out a neocloud site rather than leasing it, which would turn this week from a pair of headlines into a pattern.

Sources: Crusoe, Google, TechCrunch, Tallgrass (July 2025), Bloomberg (June 2026), Reuters via Investing.com, Investing.com, Bloomberg on Microsoft and neoclouds, Financial Times via Investing.com, Nscale (October 2025).